Planning Aluminum Coil Shipments from Aqaba: Where Port-to-Port Time Fits.

A transit time on a quote answers one question: how long the ship takes. Whether the coil is on your line on the day you need it depends on every other leg too, so the useful exercise is to schedule backward from your date.

Key takeaways

  • Orbit's port-to-port transit estimates are 5 to 13 days to Europe and about 25 days to the USA. They are estimates.
  • Port-to-port is one leg. Production, loading, discharge, clearance, inland delivery and receiving are separate legs.
  • Work backward from the date coil must be on your line, and plan to the upper end of the range if a delay would stop production.
  • Ask for production timing and shipping dates when you request a quote.

What does port-to-port transit cover?

It covers the sea leg between the loading port and the discharge port. Coil ships from Aqaba, and Orbit's port-to-port transit estimates are 5 to 13 days to Europe and about 25 days to the USA. Port-to-port means the sea leg between ports, so a figure of that kind does not cover production, inland delivery or clearance. Ask what any quoted figure includes.

Treat any transit figure on a quote as the length of one leg, and ask what is outside it.

How do you schedule backward from your line date?

Start with the date the coil must be on your line, then subtract each leg. The table uses hypothetical numbers for your side of the chain, labeled as such, to show the method.

Back-schedule example. Days for receiving, inland delivery and clearance are hypothetical placeholders. Replace them with your own.
LegEurope, upper estimateEurope, lower estimateUSA
Receiving and inspection (placeholder)2 days2 days2 days
Inland delivery (placeholder)3 days3 days3 days
Discharge and clearance (placeholder)4 days4 days4 days
Port-to-port (Orbit estimate)13 days5 daysabout 25 days
Total after loading22 days14 daysabout 34 days

Production and loading come before that total, and their timing is something to ask for in the quote request.

Why plan to a range?

The Europe estimate runs from 5 to 13 days, so the arrival date is a window, not a point. If a late arrival would stop your line, plan to the upper figure. If you can run from stock for a week, the lower figure may be acceptable. The choice is yours, and it is a business decision, not a statement about any sailing.

The Incoterms rule agreed in the quote, for example FOB, CIF or DAP, decides who arranges and pays each leg and where risk passes. It does not change the port-to-port days. The 5 to 13 day range is a stated range, so ask for the expected figure for your destination port.

What travels with the coil?

Material certificates accompany every batch, and each coil is tagged with lot and specification details. Your broker or customs agent will tell you which commercial and import documents your country requires, so ask them early and put the list in the request. The certificate guide explains how to check the certificate on arrival.

What should the RFQ say about delivery?

  • The destination port or place, and the trade terms you want quoted
  • The date coil must be on your line, and whether partial shipments are acceptable
  • Whether the order is one lot or several, so the plan covers each
  • Your handling set-up, so packing and loading can be planned. See the receiving and storage guide and the packaging and handling page.

The minimum order, 6.5 MT plus or minus 10 percent, also shapes the plan. The lot planning guide covers it.

How are the estimates used?

As a first screen, not a promise. Ask for production timing and shipping dates for the order when you request a quote. If your decision turns on a few days, ask for those dates in writing and build the buffer into your own plan. Orbit responds to RFQs within one business day.

What changes if the order ships in more than one lot?

Each lot can have its own production date, its own loading and its own sea leg. A line that needs the whole order before it can start is governed by the last lot, not the first. A line that can start on the first lot and take the rest later has more room. Say which of the two applies when you request the quote, because it decides whether partial shipments help you or only add receiving work.

Write the split into the purchase order with a quantity and a required date for each lot. A single date for the whole order hides the lots, and the schedule can only be checked against dates that are written down.

Where does the buffer belong?

Put the buffer where the uncertainty is, and say whose it is. The sea leg is a range, so it carries a buffer on your side. Clearance and inland delivery depend on your port, your broker and your carrier, so ask them for their own range and add it to the table above. Ask for production timing in the quote request. If one leg is uncertain and the others are firm, the schedule should show that leg as a range and the rest as single numbers.

A plan that adds a single large buffer at the end is harder to defend than one that shows which leg each day belongs to.

Common questions

Are the transit times guaranteed?

No. They are port-to-port estimates. Ask for dates for a specific order in your RFQ.

Do the estimates include inland delivery?

No. Port-to-port covers the sea leg. Ask what a specific quote includes. Inland delivery, clearance and receiving are separate legs.

Which ports does Orbit ship from?

Coil ships from Aqaba.

How quickly does Orbit answer a request?

RFQs are answered within one business day.

References

Orbit is an integrated aluminum coil manufacturer in Aqaba, Jordan, family owned and operating since 1976, with recycling, casting, rolling and coil coating. We hold ISO 9001, ISO 14001 and ISO 45001.

Planning a delivery date?

Send destination, required date, quantity and handling set-up. We respond to RFQs within one business day.

Request a Quote

The technical information in this article is prepared in good faith and verified against publicly available industry sources at the time of writing. Product specifications, applications and requirements can vary by project; always confirm current specifications directly with Orbit Aluminum Industries before purchasing or specifying. Orbit Aluminum Industries is not liable for decisions made or outcomes resulting from use of this content. See our Terms & Conditions.